Handover of building works in Morocco: a protocol that leaves nothing to chance

Handover is the moment you officially take possession of your house. If it is poorly prepared, you lose essential remedies. Here is how to conduct it step by step.

Published on 10 May 2026 · Updated on 9 October 2026 · Reviewed against the official texts on 9 October 2026 · By Multi Service de Marrakech Junior

Hand holding a new key in front of an arched wooden door

The handover (acceptance of works) marks the transfer of responsibility from the contractor to the client (owner). From that moment, the legal warranties start to run, and any snags not recorded at this stage are lost for good.

In Morocco, the Code of Obligations and Contracts (DOC) and the terms of the building contract govern this stage. Accepting the works without a written handover report (procès-verbal de réception) amounts to giving up most of your future remedies.

2. The handover inspection: what to check

Prepare a checklist by trade: structure (cracks, plumb), roof (waterproofing, drainage), doors and windows (play, airtightness), electrics (test every circuit, the distribution board, the sockets), plumbing (pressure, drainage, taps and fittings), floor and wall coverings (flatness, joints, no breakage), paintwork (even finish, no runs). Test everything in the contractor's presence.

Take dated photos of every defect you find. These photos are the main evidence in any later dispute about the condition of the works at handover.

3. The handover report and the snags

The report must be drawn up in two copies signed by both parties. It lists the snags (defects found) with a precise deadline for clearing them — usually 15 to 30 days. Until the snags have been cleared and checked, the final balance of the contract (the retention) should not be paid.

If the contractor refuses to sign or to record the snags, have a bailiff (huissier de justice) draw up an official report the same day. This document has the same evidential value as a report drawn up jointly by both parties.

4. Clearing the snag list: not to be confused with handover

Clearing the snag list is a second inspection, after the contractor has corrected the listed defects. It results in a second signed document confirming that the works comply. Only at this point is payment of the balance justified.

If some snags are not cleared within the agreed deadline, you can have the corrective work done by a third party and deduct the cost from the balance due. This requires a formal notice (mise en demeure) first.

5. The file to keep after handover

Be sure to keep: the signed handover report, the snag-clearance report, the delivery notes for materials, the final plans, the technical manuals for equipment (water heater, electrical distribution board, mechanical ventilation), the manufacturers' warranties and the contact details of every subcontractor who worked on the project.

This file is your protection for the next ten years: for ten years from handover, the contractor and the architect are liable for the total or partial collapse of the building, or an obvious danger of collapse, caused by a defect in the construction, the materials or the ground (DOC, article 769). Action must be brought within thirty days of the defect being discovered: keep the file and act quickly.

In summary

Multi Service de Marrakech Junior formalises every handover with a detailed report, a numbered snag list and a timetable for clearing it. The balance is only requested once compliance has been confirmed in a joint inspection.

Sources and reference texts

  • Code of Obligations and Contracts (DOC), article 769 (ten-year liability)
  • Law 46-21 on the organisation of the profession of bailiff (huissier de justice) (2025)

Cite this guide

Using this guide on your website, on a forum, for an association or in a document? Please cite the source with a link to the original page.

“Handover of building works in Morocco: a protocol that leaves nothing to chance”, Multi Service de Marrakech Junior, updated 9 October 2026. https://mmj.ma/en/blog/reception-travaux-maroc

Author

Multi Service de Marrakech Junior — All-trades construction company, Marrakech

Guides written by the company’s management, based on our experience on site, and reviewed against the official texts (Official Bulletin). They do not replace advice from a lawyer, a notary or an architect.

This article is provided for general information and does not replace advice from a lawyer, a notary or an architect. Legislation changes: check the version in force for your situation.